PINAR DEL RIO, Cuba, Nov 25 (ACN) The 99, 95 % of the clients of Pinar del Rio already have electricity service, one of the severely affected due to the scourge of Hurricane Ian, last September 27.
Fifty-nine days after the hydrometeorological event, the recovery work has been complex since the entire infrastructure was devastated, which is why the support of contingents and companies from other provinces has been vital.
There are still users in the communities of San Juan y Martinez, Consolacion del Sur, Pinar del Rio and San Luis without service, although there is little damage to be repaired in those places.
In the province, more than 6,240 poles, 760 transformers and some 87 kilometers of conductors have already been reestablished.